We have divided our journey into three sections. The Events section is for activities that have already happened to introduce the school and build the community. The Planning section shows school blueprints, and how the team has been involved in the planning process. The Construction section shows the progress of building the school.

Click on any picture to see it bigger!

Events

First Informational Night

Information Night

The first Information Night was hosted in December at Evergreen Middle School. Principal Bilanko introduced herself, and shared the vision and mission for the school.

Meeting Students

Mrs. Bilanko met with students at each elementary to introduce herself and get their help in naming the school.

Planning

School Blueprints

Pictures below show how the school was imagined before construction began.

(Click images to view larger)

Digital rendering of the property.

Digital drawing of the front of the school.

Digital drawing of the back of the school.

Virtual Planning

Principal Bilanko taking a virtual tour through the site

Using virtual technology, the planning team can see what the building will look like

Timeline

Groundbreaking

Groundbreaking: District Leadership and Principal Bilanko officially broke ground for Redmond Ridge East on June 7th

August 2017

Future RREE staff touring the site in August 2017

September 2017

Steel Construction Began in September 2017

Asphalt was poured on 9595 Eastridge Dr. N.E.

Aerial photo of the work site

October 2017

Steel structures are well underway to create the form of the school.

Structure of the main hallway.

November 2017

As of November, construction is on schedule!

Steel beams close to finished.

November aerial photo

December 2017

Topping Out Ceremony: The last steel beam shows each group that was involved with the school project.

Topping Out Ceremony: Principal Kim Bilanko signing her name on the final beam.

Topping Out Ceremony: The final beam is set in place.

Topping Out Ceremony


Just in time for the snow, the roof is finished and siding is going up.

January 2018

January aerial footage

Front of the school

Upper Pods will have an outdoor porch

Future Pod/Classroom Area

Window in the upstairs Library

Nominations for School Name


Videos

Watch the videos below to see even more about each step along our journey

Topping Out Ceremony